Optimizing Software Development Time Estimation by Integrating Function Point Analysis and Use Case Point Method

Ardiansyah M.Y.

Proceedings International Conference on Informatics and Computational Sciences

Published: 2025

Abstract

Software development time estimates are essential for project planning, but estimation accuracy is still a challenge due to the limitations of each method. Function Point Analysis (FPA) assesses the functionality of the system, while Use Case Point (UCP) focuses on user interaction. This study integrates the two to produce more accurate estimates. The analysis was carried out on 10 systems by calculating FP and UCP, then combined using a weighted formula. The integration value is converted into a time estimate and evaluated with a Mean Absolute Percentage Error (MAPE). The average MAPE of <tex xmlns:mml="http://www.w3.org/1998/Math/MathML" xmlns:xlink="http://www.w3.org/1999/xlink">$\mathbf{1 2. 2 9 \%}$</tex> shows good estimation results. This model has proven to be effective and can be an alternative in optimal time management of software projects.

Other files and links

Fingerprint

Function pointSciences
Computer scienceSciences
Point (geometry)Sciences
SoftwareSciences
Function (biology)Sciences
Software developmentSciences
EstimationSciences
Time pointSciences
Use Case PointsSciences
Point estimationSciences
Mean absolute percentage errorSciences
Data miningSciences
Mathematical optimizationSciences
Development (topology)Sciences
AlgorithmSciences
Software systemSciences
Value (mathematics)Sciences
Software development processSciences
Term (time)Sciences
StatisticsSciences